Update on 48-inch Force Main Reliability Improvement Project

  • by BPC Staff
  • on February 13, 2014
  • 0 Comments

 

Update on 48-inch Force Main Reliability Improvement Project

  February 13, 2014

SVCW provides wastewater services to residents and businesses in
Redwood City, San Carlos, Belmont, and West Bay Sanitary District

 

 

 

  

Update #23 (February 13, 2014) for  

48-inch Force Main Reliability Improvement Project:  

Unit 1 – Maple Street to Bair Island/Bair Island Road    

 

 

 Maple Street/Docktown Update

 

Construction on Maple Street is escalating. Today the contractor is pounding support beams in for the shoring system, which will generate noise and vibration. The next phase of the work will be the actual excavation on the first of three phases on Maple Street. As a result dump trucks will be loading and transporting soil away from the excavation and excavators will be moving back and forth on the street while they are digging down. This will be followed by pipe installation. This work includes the new San Mateo County Jail’s 20-inch gravity sewer in the same trench.   This first 300-foot segment will take three to four months. Most truck traffic will be from about 8 am to 4 pm though work will still be occurring there from 7 a.m. to 7 p.m. Following this first stretch, there will be two more 300-foot segments following this same procedure moving away from Highway 101.

 

Bair Island/Bair Island Road Update

 

The work on Bair Island is now inserting the HDPE pipe into the casing. The first segment is complete from Jacking Shaft #2 (located on the property owned by the U.S. Fish & Wildlife near the new pedestrian bridge) to Receiving Shaft #2 on the Island. Now the contractor is installing the pipe from Jacking Shaft #2 to Receiving Shaft #1 located at the east end of the USFWS parking lot off of Bair Island Road. The duration of this work will be to March 31. This will include filling up this jacking shaft hole to the existing ground surface. There will be limited noise for this operation, a crane operating intermittently and a loader picking up pipe and delivering it to the shaft.

 

How You Can Stay in Touch

 

            Log on onto SBSA’s website,  www.svcw.org/ and follow updates.

            Let us send you electronic updates to your email as developments happen – send us your email to duanesandul@gmail.com and ask for Pipeline Project Updates.

            Follow us on Twitter and/or Facebook.

            Follow our blog at the Redwood City-Woodside Patch:  http://redwoodcity-woodside.patch.com/blogs/sbsa-wastewater-facility 

 

 

More updates will follow as the work progresses.   

 

 

 

 

 

 

 

Questions About the 48-Inch Pipeline Project

Duane Sandul  650-585-2181
duanesandul@gmail.com

The mission of the 48-Inch Force Main Reliability Improvement Project is to plan, design, construct, and safely put into service, at the lowest reasonable cost and in the shortest practical time, a new force main pipe that protects the environment.

 

 

http://www.sbsa.org/48-inch-pipeline/ 

 

South Bayside System Authority
1400 Radio Road
Redwood City, CA 94065
Phone: 650-591-7121
www.sbsa.org

STAY CONNECTED